Even though FRP and dual-laminate pipes and tanks are widely used in chemical plants, each customer has a different approach to requesting quotes and managing the project during design and fabrication. Shahin Shadlou of RPS Composites discusses best practices.
Clear, detailed technical specifications—referencing ASME RTP-1, ASTM D3299, and ASME B31.3—are essential to ensure all bidding fabricators estimate on an equal quality footing.
The presentation highlights key contract milestones, pre-fabrication submittal reviews, resin verification certificates, and third-party inspection checkpoints during procurement.